Engineering Beyond the Obvious – Delivering Precision Power Solutions for a Leading Battery Manufacturer

A major battery manufacturer approached Johnson & Phillips with a critical issue: the existing supply circuit feeding their rectifier chargers was regularly overloaded and experiencing nuisance tripping. The initial goal was to upgrade the infrastructure to meet operational demands. The expectation was clear — increase the circuit capacity.

The challenge

Initial Assessment & Proposal

Upon initial review, the overloaded 630A circuit required significant intervention.

A conventional upgrade would have involved costly and disruptive works. J&P priced this traditional solution at approximately £72,000, taking into account the challenging installation and site-specific complexities.

The client was ready — the order was issued without hesitation.

But we said no.

Engineering-Led Integrity

As engineers, we couldn’t proceed blindly. We proposed a Power Analysis to better understand the true source of the problem. The results were eye-opening:

  • The 630A circuit was operating at 645A — beyond design limits.
  • Conductor temperature had risen to 70°C, presenting a long-term risk.
  • Power Factor was a shocking 0.3, highlighting excessive reactive power and inefficiency.

This wasn’t just a case of undersized infrastructure — it was a Power Quality issue in disguise.

The solution

Alternative Solution: Smarter, Cleaner, Cheaper

Armed with real data, we proposed a more intelligent approach:

  • Install a Hybrid Digital Compensator at the load side.
  • Cost: Approximately £38,000, nearly half the original proposal.
  • Delivery: Completed and commissioned within one week.

The Client’s Reaction?

“You’re either mad or geniuses.”

We let the outcome do the talking.

Engineering Beyond the Obvious

The result

Results: Performance Transformed

The impact was immediate:

  • 70% of the ‘dirty load’ was neutralised at source.
  • Conductor temperatures dropped to ambient.
  • Nuisance tripping stopped completely.

The Moral

Don’t throw copper at a power problem. Understand it.

With deep technical insight and a commitment to getting it right, Johnson & Phillips delivered a solution that:

  • Cut costs by over £30,000
  • Reduced operational risk
  • Improved efficiency and resilience — all without unnecessary infrastructure works

We Are Johnson & Phillips

Power is more than what we deliver — it’s who we are.

From transformers to PFC, from resilience to power quality, we engineer better outcomes.

We are J&P. We are engineers.

Lights out? We answer.

Network failure, tripped protection or a site that has gone dark. Our disaster recovery engineers are on call every hour of every day, arriving in minutes, not hours.

24/7 Emergency Line 01900 247 365